Group Housing Requirements: What Is Checked Before Licensing

Group housing requirements in Saudi Arabia: what Balady reviews before licensing, what inspectors check, and how to license or contract licensed housing.

Mnzil workforce housing building in Riyadh (RUH-UMH-1003)

Under the group housing requirements, licensed housing is mandatory for establishments with 20 or more workers, applied in phases, with the final phase starting on 1 February 2027. You can comply by licensing your own building on Balady, or by contracting units that are already licensed. Either way, your workers need housing with a valid licence that covers their number.

The short answer: two lawful paths

According to the National Program for the Development of Group Housing for Individuals, licensed group housing is mandatory for establishments that have 20 workers or more. The program has set two paths for regularising worker housing:

  • First path: Obtaining a group housing licence for the building that belongs to the establishment through the approved platforms, after meeting the health, technical and safety requirements.

  • Second path: Contracting with group housing units that are already licensed, without needing to manage housing facilities of the establishment's own.

So you are not required to own a building or to license it. What you are required to have is housing for your workers with a valid licence that covers their number. And if you want ready housing for your workers without taking on the licensing yourself, contact Mnzil.

Steps to obtain a group housing licence from Balady

The service "Issuing a Group Housing Licence for Individuals" is electronic only, and it is submitted by the property owner or the tenant. These are the steps as published by the Balady platform:

  1. Go to the dashboard and choose your user capacity.

  2. Choose the service through "New Submission".

  3. Fill in the application details and send it to the municipality.

  4. The competent municipality checks that the site complies with the spatial requirements, then approves or returns the application with comments.

  5. Complete the application within the set deadline after the initial approval is issued.

  6. The municipality or the engineering office (depending on the track) receives the application and completes the procedure until the licence is issued.

Documents to prepare before you start, as listed by the Balady platform: a commercial register (if the applicant is an establishment), the coordinates of the housing, the detailed data (property type, built-up area, number of rooms and their area, number of bathrooms), the title deed or lease contract, photos of the housing, and the safety permit.

The operating licence conditions include a valid commercial register that has the group housing for individuals activity, the availability of the spatial planning requirements, the building completion certificate, and Civil Defense approval before the licence is issued.

Before you sign a lease or purchase contract, use the service "Inquiry about Requirements and Prohibited Areas for Group Housing Licences" on the Balady platform, so you know whether the site falls in a prohibited area before you commit to it. The fees are calculated from the fee calculator on the platform. For the full process, see the Worker Housing Permit in Saudi Arabia: Step-by-Step Licensing Guide.

What the authorities review before licensing and during inspection

The practical division: before licensing, the paperwork and the site are reviewed; after licensing, the reality on the ground is inspected, along with how far it matches the licence. According to the Balady platform, violations are recorded according to how far the housing complies with the licence requirements and the health, technical and safety conditions.

Stage

What is reviewed

Authority

Before licensing

That the site complies with the location requirements and is not in a prohibited zone

The municipality through the Balady platform

Before licensing

The building completion certificate and a commercial registration that includes the group housing activity

The Balady platform

Before licensing

Civil Defense approval and a safety permit

Civil Defense

Before licensing

The capacity, which is set according to the area of the building or complex

The Balady platform

During inspection

A valid licence that matches the number of residents and the number of workers registered in Qiwa

The inspection committee

During inspection

The space allocated to each worker in the housing, and the number of toilets

The inspection committee

During inspection

A laundry room equipped with a washing machine and drainage, or the provision of a laundry service

The inspection committee

During inspection

A first-aid room or clinic in large housing

The inspection committee

During inspection

Cracks or leaks that threaten the safety of the residents

The inspection committee

The minimum bedroom area per person, and the maximum number of people in a room, can be found in the guide to health, technical and safety requirements for group housing for individuals, published on the website of the Ministry of Municipalities and Housing. Do not rely on a figure circulating in an article or a conversation, and refer to the version of the guide currently in force.

Must you license the building, or is contracting licensed housing enough?

The decision depends on your relationship to the building, the size of your workforce and how long you need the housing, and there is no single answer that suits every establishment.

  • Licensing the building suits you if you own a property designated for housing or lease a whole building on a long contract, and you have a team that follows up the licence, the safety permit and renewal. You gain more control over layout and maintenance, and you bear the follow-up of every requirement.

  • Contracting with group housing units that are already licensed suits you if your workforce changes from project to project, or you do not want to operate a housing facility, or time is short before the compliance deadline.

Who bears the violation? Group housing violations fall on the holder of the right of use: the building owner if the units are leased to several parties, the tenant if a single party leases the whole building, and the project contractor in mobile cabins. This is why it makes a big difference whether you rent units inside a building whose licence is held by someone else, or rent the whole building and become the holder of the right of use.

What should you ask for when contracting? Ask for a copy of the licence and its expiry date, compare its address with the building you visited, and compare the licensed capacity with the number of beds on offer. If you rent units in a licensed property, the Balady platform offers the service "Issue a certificate proving group housing for individuals", and the certificate is issued with the group housing licence number of the property. The certificate proves your connection to licensed housing and does not replace the licence.

Note also that the requirement covers the establishment and all of its branches, as well as commercial registrations unified under a single number, and that the approved workforce count is the one registered in Qiwa.

How compliance is checked, and what is required before 1 February 2027

How is compliance checked?

According to the Ministry of Municipalities and Housing, the electronic link between the Balady platform and Qiwa makes it possible to verify compliance, and a business's commercial registration is suspended if there is no valid group housing licence that matches the capacity and the number of registered workers.

In practice: make sure that the housing licence is valid and that its capacity covers the number of workers registered in Qiwa. Because procedures are updated, check with Balady and Qiwa for the rules currently in force.

What is required before 1 February 2027

The National Programme for Developing Group Housing for Individuals has announced that the businesses targeted in the final phase are required to correct their worker housing situation before this phase begins on 1 February 2027, and that the current period is a corrective grace period. If time is short ahead of the deadline, contact Mnzil to find out which units are available in your city. You can build your plan in this order:

  • Count your workers: the number of workers registered in Qiwa, and where each of them lives today.

  • Check every site: whether it holds a valid group housing licence, and whether its capacity covers the number of people actually living there.

  • Choose the path for each site: license the building, or move the workers to pre-licensed units.

  • Document the relationship: a proof-of-housing certificate for rented units.

  • Start early: there is a set period to complete the licence application after initial approval, so do not start in the last week.

Worker housing violations, fines and a checklist

Worker housing violations and fines

The Ministry of Municipalities and Housing's guide for inspecting group housing for individuals is advisory. It guides the inspection committees on violations and how they are handled:

  • Fine amount: It varies by the type of violation, the category of the municipality and the size of the facility, and it is highest for operating group housing without a licence or after the licence has expired.

  • By size and location: The guide's fines for first-category cities (Riyadh, Makkah, Madinah, Jeddah, Dammam, Khobar and Dhahran) are higher than elsewhere, and the fine rises as the facility gets larger.

  • Gradation: A non-serious violation starts with a warning and a grace period to correct it before a fine is imposed, whereas a serious violation is fined immediately.

  • Repetition: The fine is doubled when the same violation is repeated.

  • Closure: The permanent inspection committee may close the housing if it is operating without a licence, if the minimum bedroom area is not provided, or if there are cracks and leaks that threaten safety. It may also propose a prison sentence and refer the case to the Public Prosecution.

  • Registration and payment: Violations are recorded on the Ministry's Mumtathil platform, and fines are issued for payment through the Eyfa platform.

  • Objection: A person who has been issued a violation objects before the Administrative Court in accordance with the Law of Procedure before the Board of Grievances.

Checklist of steps

  1. Record the number of workers registered in Qiwa and the number expected during the contract period.

  2. Check the requirements and the prohibited areas on the Balady platform before signing any contract.

  3. Request the group housing licence in writing, and verify the address, the expiry date and the capacity.

  4. Request the safety permit and the Civil Defense approval.

  5. Visit the building and compare the room sizes, the number of bathrooms and the laundry room with what is stated in the licence and the guide.

  6. If you rent units, issue the proof-of-housing certificate from the Balady platform using the property licence number.

  7. State in the contract who renews the licence, and who bears the cost of moving the workers if the building is closed.

If you want another party to take over this follow-up, Mnzil offers furnished group housing units on a pay-per-bed basis, with the bed price starting from 11 riyals per day, and every unit has a dedicated laundry area with washing machines. For those who own a building, Mnzil offers the "Run My Unit" service, which manages the building completely and takes care of utility bills, maintenance contracts, security and administration, moving from audit to full operation within 14 days at most. As you would with any provider, ask for the licence number and its date for each site, and visit the site before signing.

Talk to Mnzil

Frequently asked questions

How do I obtain a group housing licence for workers from the Balady platform?

Go to the Balady platform dashboard, choose the service "Issue a group housing licence for individuals" through "New request", then fill in the request details and send it to the municipality. The municipality checks that the site meets the spatial requirements, then completes the request after preliminary approval until the licence is issued.

We have more than 20 workers: must we license the building, or is contracting licensed housing enough?

Both options are lawful. You can license the building that belongs to your establishment through the Balady platform after meeting the health, technical and safety requirements, or contract with group housing units that are already licensed. What matters is that your workers live in a building with a valid licence covering their number.

What happens if an establishment has no valid group housing licence?

According to the Ministry of Municipalities and Housing, the electronic link between Balady and Qiwa is used to verify compliance. The commercial registration is suspended if there is no valid group housing licence that matches the capacity and the number of registered workers.

What must an establishment do to correct its worker housing before February 2027?

Count your workers registered in Qiwa, check each site's licence and its capacity, then choose for each site between licensing the building and moving the workers to pre-licensed units. The corrective grace period ends when the final phase of enforcement begins on 1 February 2027.

How many workers are allowed in one room under the group housing requirements?

The Health, Technical and Safety Requirements Guide for Group Housing for Individuals sets the minimum bedroom area per person and the maximum number of people per room. Refer to the current version of the guide on the Ministry of Municipalities and Housing website, and compare the number of residents with the capacity stated in the licence.

What do inspectors check in worker housing?

Inspectors check that there is a valid licence matching the number of residents and the workers registered in Qiwa, that there are enough bathrooms, that there is an equipped laundry room or a laundry service, and that the building is free of cracks and leaks that threaten the residents' safety.

Is Mnzil housing compliant with the group housing requirements?

Yes. Mnzil provides housing that meets and complies with the municipal requirements for group housing. It is fully furnished and ready to move in from day one, with utilities, maintenance and 24/7 support included. For more details on the sites available in your city, contact Mnzil.

Talk to Mnzil

Need housing for your workforce?Housing, catering and transport in one contract, close to your project site.Contact us

Related articles

General

Staff Accommodation in Jeddah: Housing a Mixed Workforce

Staff accommodation in Jeddah: what employers must provide, who is responsible for safe, hygienic housing, and the licence and room checks to make before you sign.

Read more
General

Catering Services in Riyadh: Picking a Worker Meal Provider

Catering services in Riyadh for worker crews: compare meal options, menus, delivery to camps and sites, and what to check in a contract before you sign.

Read more
General

How Much Is the Fine for a Worker Housing Violation in Jeddah?

A housing violation notice landed at your Jeddah worker building. Learn where the fine amount is set, what makes it grow, and how to check and act fast.

Read more

Want to get in touch?

Contact us